Cost Estimation


Cost Estimation

Chemical Engineering projects

            Before the plant to be operated, specified money must be supplied to purchase and install the equipment. The capital needed to supply the necessary plant facilities is called fixed capital investment while that for the operation of the plant is called the working principal and sum of two capitals is called total capital investment.

An acceptable plant design must present a process that is capable of operating under conditions which will yield a profit. Since, Net profit =total income – all expenses

It is essential that chemical engineer be aware of the many different types of cost involved in manufacturing processes. Capital must be allocated for direct plant expenses; such as those for raw materials, labor, and equipment. Besides direct expenses, many other indirect expenses are incurred, and these must be included if a complete analysis of the total cost is to be obtained. Some examples of these indirect expenses are administrative salaries, product distribution costs and cost for interplant communication.

ESTIMATION OF EQUIPMENT COST

Cost index used for 1999 = 109

Cost index used for 2009 = 121

11.1. CSTR-1:

Purchased equipment cost = Ce = CSn

Cost constant = C = $ 31000

Area of column = S = 5m3

Index = n = 0.40

Ce = CSn

Ce = CS0.40

= 31000 (5)0.40

Ce = $ 59013.27

Ce (2009) = 59013.27 x (121/109) = $ 10005

11.2. Distillation column D-1:

Number of plates = 5

Reflux ratio = 2

Bare vessel cost = $ 9000

Diameter of column = 0.6 m

Height of column =10 m

Material: Carbon steel

Material factor = 1.0

Pressure factor = 1.4 at 26.67 bar

Vessel cost = 9000 x 1.4 x 1.0 = $ 12600

Cost in 2009 = 12600 x (121/109) = $ 13987

Sieve plate: one plate cost = $ 310

Material factor = 1.0

Total cost of one plates = $ 1550

Total cost of five plates (2009) = $1550 x (121/109) = $ 1720

Total column cost = 12600 + 1550 = $ 14150

Total column cost (2009) = 14150 x (121/109) = $ 15707

Condenser:

Area = A = 2.8737 m2

Pressure factor = 1.1

Type factor = 0.8

Bare cost = $ 1050

Cost of equipment = 1050 x 1.1 x 0.8 = $ 924

Cost of equipment (2009) = 1050 x (121/109) = $ 1026

Reboiler:

Required area = A = 0.774 m2

Pressure factor = 1.1

Type factor = 0.85

Bare cost = $ 428.57

Cost of equipment = 428 x 1.1 x 0.85 = $ 400.7

Cost of equipment (2009) = 400.7 x (121/109) = $ 444

11.3. Distillation column D-2:

Number of plates = 6

Reflux ratio = 2

Diameter of column = 0.67 m

Height of column = 7 m

Bare vessel cost = $ 9000

Material: Carbon steel

Material factor =1.0

Pressure factor = 1.4 at 26.67 bar

Vessel cost = 9000 x 1.4 x 1.0 = $ 12600

Cost in 2009 = 12600 x (121/109) = $ 13987

Sieve plate: Cost of one plate = $ 310

Material factor = 1.0

Total cost of 12 plates = $ 3720

Total cost of 12 plates (2009) = 1240 x (121/109) = $ 4130

Total column cost = 12600 + 3720 = $ 16320

Total column cost (2009) = 13840 x (121/109) = $ 18116

Total plates costs = $ 3720

Bare vessel cost = $ 13987

Total vessel cost = $ 15363

Condenser:

Area = A = 2.8737 m2

Pressure factor = 1.1

Type factor = 0.8

Bare cost = $ 1050

Cost of equipment = 1050 x 1.1 x 0.8 = $ 924

Cost of equipment (2009) = 1050 x (121/109) = $ 1026

Reboiler:

Required area = A = 0.774 m2

Pressure factor = 1.1

Type factor = 0.85

Bare cost = $ 428.57

Cost of equipment = 428 x 1.1 x 0.85 = $ 400.7

Cost of equipment (2009) = 400.7 x (121/109) = $ 444

11.4 Gravity separator X-1, X-2:

Number of units = 2

Equipment cost (2009) = $ 2000

Total cost of two units = $ 4000

11.5 Distillation column D-1:

Number of plates = 5

Reflux ratio = 2

Bare vessel cost = $ 9000

Diameter of column = 0.6 m

Height of column = 10 m

Material: Carbon steel

Material factor =1.0

Pressure factor = 1.4 at 26.67 bar

Vessel cost = 9000 x 1.4 x 1.0 = $ 12600

Cost in 2009 = 12600 x (121/109) = $ 13987

Sieve plate: Cost of one plate = $ 310

Material factor = 1.0

Total cost of five plates = $ 1550

Total cost of five plates (2009) = 1550 x (121/109) = $ 1720

Total column cost = 12600 + 1550 = $ 14150.

Total column cost (2009) = 14150 x (121/109) = $ 15707

Condenser:

Area = A = 2.8737 m2

Pressure factor = 1.1

Type factor = 0.8

Bare cost = $ 1050

Cost of equipment = 1050 x 1.1 x 0.8 = $ 924

Cost of equipment (2009) = 1050 x (121/109) = $ 1026

Reboiler:

Required area = A = 0.774 m2

Pressure factor = 1.1

Type factor = 0.85

Bare cost = $ 428.57

Cost of equipment = 428 x 1.1 x 0.85 = $ 400.7

Cost of equipment (2009) = 400.7 x (121/109) = $ 444.

11.6 PUMPS P-1, P-2, P-3, P-4:

Number of pumps = 4

Type: horizontal one stage

Diameter of discharge pipe = 3 in.

Material of construction: stainless steel

Seal type: mechanical seal

Cost (2008) = $ 4700

Cost (2009) = $ 4700 x (121/119) = $ 4780

Cost (2009) of 4 pumps = $19120

11.7 Neutralization Reactor MFR-2:

Purchased equipment cost Ce = CSn

Cost constant C = $31000

S = 5 m3

n = 0.40

Ce = CS0.40

Ce = 31000 (5)0.40

Ce = $ 59013.27

Ce (2009) = 59013.27 x (121/109) = $ 10005

11.8. Mixer Mix-1, 2, 3:

Number of units = 3

Equipment cost (2009) = $ 1500

Total cost of three units = $ 4500

11.9. Double pipe heat exchanger E-1:

Pipe inner diameter = 2 ½ in.

Area of one exchanger = 24 ft2

Purchased cost of one exchanger = $ 1000

Total purchased cost of one exchanger (2009) = 1000 x (121/109) = $ 1110.09

Total no. of heat exchangers = 1

Total purchased cost of two exchangers = $ 1110.09

11.10 Liq-Liq Extractor:

Equipment cost = $ 3000

11.11 Estimation of fixed capital cost:

Sr. no. Items

Process type fluids

1 Major equipment, total purchase cost

PCE

F1 equipment erection

0.4

F2 piping

0.70

F3 instrumentation

0.20

F4 electrical

0.10

F5 buildings , process

0.15

F6 utilities

0.50

F7 storages

0.15

F8 site development

0.05

F9 ancillary buildings

0.15

2 Total physical plant cost ( PPC) = PCE ( 1+ F1…+F9)

= PCE x 3.40

F10 design and engineering

0.30

F11 contractors fee

0.05

F12 contingency

0.10

Fixed capital= PPC(1+F10+F11+F12)

= PPC x 1.45

Total purchased cost of major equipment items (PCE):

EQUIPMENTS

TOTAL PURCHASED COST ($)

CSTR

10005

Distillation columns (3)

51187

Gravity separator (2)

4000

Pumps (4)

19120

Neutralization reactor

10005

Mixer (3)

4500

Double pipe heat exchanger (1)

1110

Water washing column

3000

Total purchase cost of major equipment

102927

PPC = PCE x 3.40

PPC = 102927 x 3.40

PPC = $ 349951

Fixed capital = 349951 x 1.45

Fixed capital = $ 507430.11

Total initial investment required for project = $ 507430.11

Chemical Engineering projects

4 thoughts on “Cost Estimation”

  1. donde puedo obtener literatura de costos esimados porque tengo libros muy antiguos

Leave a comment